TOTAL RECLAIMS DEMOLITION Ltd
RUGBY RAILWAY BRIDGE

The Rugby Railway Bridge was completed on time. The Director Mark Cross felt this proect was so important he decided to head the project due to strict deadlines and health and safety.
After looking at the project with his health and safety officer stella wright they decided to attack the bridge with a brokk, cranes and skips to load away the steel and hardcore.
Whilst the project was running on time TRD hit a glitch because the lorries they ordered decided not to turn up. With the strict deadline on the railway being reopended he called on the Vast lorries of Total Aggregates four 8 wheelers coming down the M1 to rescue the deadline.
The project was completed on time and the client Danner and Walsh was more than happy with end result. Mark quoted " we had the best of the TRD team down here and without their help and knowledge this project could have gone over the deadline which would have been a disater with all the bad press Network Rail have had lately".
To see more pictures please click on this link. www.totalreclaimsdemolition.co.uk/rugby_project.html
Above is a picture of the bridge